풍력발전사업의 주요 장애요인 분석과 시사점
- 풍력발전 사업주체의 관점에서 -
Major Barrier Analysis and Implications of Wind Power Projects in South Korea
- From the Perspective of the Wind Power Business Entity -
박성우* , 전의찬**†
Park, Seong-Woo* , Jeon, Eui-Chan**†
Wind power projects are hindered by various required licenses and permits, local acceptance, and grid connection. In a
survey on 240 projects for which power generation business licenses were permitted, 123 projects (7,053.8 MW), 51.3% of the
total, have been delayed, suspended, or stopped. Of the 79 projects classified as delayed, 33 projects (1,655.3 MW) have been
suffering from regulated areas, and 34 projects (2,346.9 MW) have difficulty securing local acceptance. 11 projects (889.7 MW)
have difficulties in consulting with other organizations, and 21 projects (1,623.7 MW) responded that they had been delayed
due to other reasons such as not securing grid connection or disputes with other companies.
To prevent delays of wind power projects, it is necessary to establish and consistently apply clear regulations and to closely
review the regulations applied to wind farms before permitting power generation business licenses. In addition, developers
should communicate with residents from the initial stage of the project and minimize noise and environmental and landscape
damage. Distance requirements need to be adjusted based on the surrounding circumstances, and a specific power infrastructure
construction plan needs to be prepared for offshore wind power projects, which are rapidly increasing.
Barrier Analysis, Grid Connection, Local Acceptance, Regulated Areas, Wind Power